" ... shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto... "
Cases Decided in the Court of Claims of the United States - Pàgina 396
per United States. Court of Claims - 1948
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volum 121

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 pàgines
...contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain...such an extension, and his findings of facts thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the...
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volum 147

United States. Court of Claims, Audrey Bernhardt - 1962 - 712 pàgines
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Visualització completa - Sobre aquest llibre

Cases Decided in the Court of Claims of the United States, Volum 107

United States. Court of Claims - 1947 - 806 pàgines
...Case of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volum 145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 pàgines
...settlement of the contract) notify the contracting officer in writing of the 145 C. Cte. Findings of Fact causes of delay, who shall ascertain the facts and...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Visualització completa - Sobre aquest llibre

Cases Decided in the Court of Claims of the United States, Volum 94

United States. Court of Claims - 1942 - 818 pàgines
...notify the contracting officer in writing of the causes 04 C. CIS. Reporter's Statement of the Case of delay, who shall ascertain the facts and the extent...fact justify such an extension, and his findings of fact shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by...
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volum 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 pàgines
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volum 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 pàgines
...Contract) notify the Contracting Officer in writing of the causes of delay, 122 C. Gig. Finding! of Fact who shall ascertain the facts and the extent of the...fact justify such an extension, and his findings of fact thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30...
Visualització completa - Sobre aquest llibre

Cases Decided in the United States Court of Claims ... with ..., Volums 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 pàgines
...and unusually severe weather or delays of subcontractors due to such causes. The contracting officer shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty...
Visualització completa - Sobre aquest llibre

Cases Decided in the Court of Claims of the United States, Volum 104

United States. Court of Claims - 1946 - 936 pàgines
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Visualització completa - Sobre aquest llibre

Cases Decided in the Court of Claims of the United States, Volum 105

United States. Court of Claims - 1946 - 920 pàgines
...because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts and the extent of the delay...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...